Date | Area | Description |
01-Aug-16 | SPE | The VPH substrates arrived at KOSI. |
29-Jul-16 | PRI | The tender documentation for the PFC construction and assembly has been completed and is now with the IAC Administration for publication. |
26-Jul-16 | SPE | The VPH substrates, that were received on the 25th, were sent to KOSI. |
25-Jul-16 | SPE | ASTRON received five red-coated VPH substrates from Schott. A visual inspection indicates that they are all fine. |
15-Jul-16 | SPE | Schott informed ASTRON that a problem with their coating machine meant that it will be very difficult for them to deliver the VPH substrates in time for shipment to KOSI by the 15th July. |
13-Jul-16 | FIB | GEPI signed a contract with the French company SEDI for the procurement of the MOS and mIFU bare fibre. |
09-Nov-16 | WAS | The FDR meeting for the WEAVE Archive System at the University of Groningen |
22-Nov-16 | MAN | The WEAVE Boarding meeting at the University of Oxford |
28-Nov-16 | MAN | WoW: the Week of WEAVE. Click here for more details. |
19-Dec-16 | MAN | WEAVE All-Hands Meeting. Click here for more details. |