GRACE
The new AO controlled environment on the WHT for NAOMI/OASIS, GRACE (GRound-based
Adaptive optics Controlled Environment) is a project to set up at the
WHT Nasmyth 2 platform, currently occupied by the Utrecht Echelle
Spectrograph (UES), a dedicated structure designed to facilitate the
routine use of AO using ING's planned instrument suite
(NAOMI/OSCA/INGRID/OASIS).
The design of GRACE allows for the future deployment of laser guide
stars. The core of the project is to remove UES from the WHT Nasmyth 2
platform and construct a building to enclose the instrumentation and
electronics. The building will be similar to GHRIL (Ground-based High
Resolution Imaging Laboratory) on the WHT's Nasymth 1 platform but
optimised for its contents. The building will be sealed to the telescope
and have a suitably controlled environment for AO.
Gains from the project include:
- AO suite fixed in place facilitating service observing matched to
seeing.
- No physical instrument changes needed, except for INGRID.
- Controlled environment for AO.
GRACE will be a prefabricated or modular building with internal
partitions for electronics, and a seal on the optical path. Access for
major items NAOMI, OASIS etc is from the overhead crane via hinged doors
in the roof. For smaller and lighter units there is a double door, with
a single personnel door large enough to take a liquid nitrogen dewer.
Services needed GRACE will provide the following services to the AO
suite:
- Electricity 220v 50Hz Single Phase, neutral and earth
- Cooling by water/glycol circuit - electronics rooms controlled
temperature
- AO instrument area controlled to track dome temperature with
environmental monitoring/control system.
- Water glycol circuit directly connected to cooling circuits of
equipment in the AO instrument area
- Instrument air 7 bar gauge dry air, for pneumatic operation of
mechanisms and detector window anti-condensation flow
- Liquid nitrogen for detector cooling supplied from mobile dewer,
oxygen alarm for personnel protection
- Lighting
- Computer network
- Helium lines for the INGRID closed cycle cooler
- Telephone
The programme for GRACE is:
- PROJECT LAUNCH 1-Jul-2001
- BUILDING DESIGN COMPLETE 31-Aug-2001 30-Sep-2001
- BUILDING DELIVERED AND INVOICED 31-Mar-2002
- FLOOR AND SYSTEMS DESIGN COMPLETE 30-Apr-2002
- FLOOR AND SYSTEMS MATERIAL ORDERED 31-May-2002
- FLOOR AND SYSTEMS MATERIAL DELIVERED 31-Jul-2002
- LAST AVAILABLE DATE FOR UES 31-Jul-2002
- UES REMOVED AND PLATFORM CLEARED 31-Aug-2002
- ASSEMBLE BUILDING AND TEST SYSTEMS 31-Oct-2002
- INSTALL NAOMI 30-Nov-2002 INSTALL OASIS 31-Dec-2002
|