no. | Identification component | Problem | Responsible | Cost | Status |
1 | Distribution board connection checks | Loose connections cause fire hazard | 780 | 50% INT completed | |
2 | Replace emergency lighting units with dual feed | Dual feed could cause electrical danger | contractor | 1,540 | contractor identified needs planning |
3 | Voltage returns within distribution boards | Could be caused by item no.4 | contractor | 540 | Completed |
4 | Cable colour coding | Does not comply with current standard | contractor | 3,120 | Generator house + INT completed |
5 | Emergency lighting at fire extinguishers | contractor | 8,447 | ||
6 | Mains supply earth and neutral bonding | earth & neutral connect together in distribution room | ING | low | Completed |
7 | Replace circuit breakers (including replacing distribution boards) | Rated to low | contractor | 14,640 | |
8 | |||||
9 | |||||
10 |
Revision History |
|
Version Number |
Revision date |
Previous revision date |
Summary of Changes |
Changes marked |
1.00 | 04/06/08 | N/A | Document created | Michiel |
1.10 | 10/06/08 | 04/06/08 | progress updates | Michiel |
1.20 |
28/08/08 |
10/06/08 |
progress updates |
|