Autofib 2/WYFFOS Telescope Instrument Setup Procedure
Section 5 : Installing AF2 part 2/2
This sections gives instructions for the second part of the installation
procedure.
Fit Ancillary items at top end
-
Fit the swans neck.
-
Fit A&G controller support frame and install CCD controller.
-
Place the top end ring working platform in place and bolt down
-
Install Westinghouse TV system.
Cable-UP Top end.
-
Prime Focus Unit to AF2 Robot, A/G Controller, A/G Head.
-
Dry Air feed to A/G head.
-
Cable up Autoguider. Fibre connects to prime 1.
-
Connections to the Westinghouse TV and interface box
Connect up Science and Guide TV fibres.
-
Clear area and ensure only change staff are present.
-
Lay out all the fibres on the floor.
-
Run the blue science fibres from AF2 up to the break out plate.
-
Run the black guide fibre in the up to the Westinghouse TV.
-
Great care must be take when handling the fibres.
-
Using cable ties secure all the fibres ( where the metal connector joins
the grey mesh) at the end of the swan's neck. Ensure the cable ties are
on the metal part not on the grey mesh.
-
Ensure the black fibre storage centre section gaps are taped up so there
is a continuous circle, so no fibre can snag.
-
Very important. Move rotator locally to +/- limits. Check fibres twist
OK. When A&G is at the top the rotator PA should be 90 degrees.
-
Remove top end ring working platform.
Balance Telescope.
-
Drive weights to the bottom.
-
Paper calculation on moments removed and added.
-
Release telescope ties when you are sure telescope is near to balance and
slightly bottom end heavy.
-
Check top to bottom
-
Check across cube
-
Check top to bottom
This concludes the Installation of AF2 on to the telescope. The final
thing to do is to check that the instrument works, see Section
6