Timeline

 

Last update: 01 Nov 2017

Aug 2018Commissioning finishes
Jun 2019  Science operations begin
May 2019First light
May 2019Commissioning starts
Apr 2019Fibre positioner ready for commissioning
Mar 2019MOS fibres installation on Plate B
Feb 2019Spectrograph ready for commissioning
Sep 2018Assembled corrector arrives at the WHT
Jul 2018MOS fibres installation on Plate A
Aug 2018Rotator arrives at the WHT
Jul 2018LIFU installation
Jan 2018SPA meeting 6
Jan 2018WEAVE rotator FDR
Jan 2018Prime Focus Corrector System top-level review
Nov 2017Corrector assembly FDR
Mar 2017OCS FDR
Jan 2016First component (handling trolley) arrives at the WHT
Mar 2015Conference: "Multi-Object Spectroscopy in the Next Decade: Big Questions, Large Surveys and Wide Fields"
Apr 2014Blank for prime-focus corrector lens 1 is ordered
Mar 2014Science CCDs are ordered
Feb 2014First MOS fibre prototype
Jan 2014Final spectrograph optical design
Dec 2013GAIA launch
Nov 2013Five of the six prime-focus corrector blanks are ordered
Jul 2013Final prime-focus optical design
Mar 2013Preliminary design completion
Oct 2012Workshop: "La Palma and Calar Alto Observatories, Science in the Next Decade"
Dec 2011Science case delivery
Sep 2011Kick-off meeting
Mar 2010Workshop: "Science with the William Herschel Telescope 2010-2020"
Sep 2008Report by the European Telescope Strategic Review Committee of ASTRONET on "Europe's 2-4m Telescopes Over the Decade to 2020"
 

 