Mission Critical Systems, Operations


Introduction

This document lists all the mission critical systems of Operations.

Scope

Only items that are maintained by the Operations Group are included in this document.

Equipment

Item Purpose Reason Location Status
Tercery mirror collecting light no spare WHT a silver coated new Tercery being investigated (HARPS)
Aluminising plant control electronics Aluminizing mirrors failure could prevent cleaned, unique mirror from being aluminized WHT no spare controls; repair will be required on component level
AZ motor; EL motor drive system spare motor damaged WHT planned to investigate; repair & test
Flip ring motor Turning flip ring no spare WHT no spare
Decon lubrication unit Lubricating WHT telescope gears no spare WHT Michiel is evaluating spare unit
Hydraulic gear flow dividers delivering constant flow to support pads no spare WHT Michiel is evaluating spare
Marconi power amplifiers; 2 used for AZ; 2 for Elevation drive system special built amplifiers by Marconi for WHT WHT 1 spare only for 4 in use
Clip center interconnection area Telescope cables ending on tag-strips or connectors all specially wired for the WHT Lack of documentation; changes made in past not updated. Difficult fault finding. WHT requires revision, mayor job
Alarms and interlocks crate Center where all the position-, limit- and emergency- switches and indicators are wire in Custom made for the WHT by RGO. WHT no spare rack; built using wire wrapping technique
Marconi servo control rack Custom build by Marconi Custom build by Marconi. Difficult fault finding. WHT no spare rack
Focus motor focus drive no spare WHT no spare
         

References


Document Location

This document is only valid on the day it was printed.
The source of the document can be found at :

http://www.ing.iac.es/~eng/spares/Ops_Critical_Systems.htm

 

Revision History

 

                

Version number

Revision date

Previous revision date

Summary of changes

Changes marked

1.00

30 Apr 08

N/A

Document reviewed and released

JR

         

 

Approvals

This document requires the following approvals.

 

Name

Signature

Title

Date of Issue

René Rutten

 

Director

30 Apr 08

Juerg Rey   Head of Operations 30 Apr 08
Juan Martínez   Head of Administration 30 Apr 08

Don Carlos Abrams

 

Head of Engineering

30 Apr 08