NAOMI Semester 03B Engineering Program
The following table shows the taks that are planned to be tackled during
the 03B semester. Each task has been placed into the Project Issue
Management System (PIMS).
Each task has a link which should given more information on the task.
This should be a way of keeping up to date on the progress of each
issue. Everyone is encouraged to use PIMS.
Task |
Priority |
PIMS Issue |
Description |
PG
|
L
|
IUF |
RST |
IM |
Risks |
Cost |
ING Effort |
External Effort |
Due By |
NAVIS
Upgrade |
2 | 375 |
Replacing
NAVIS with a dual 1.2GHz, 2Gb DIMM Sunblade 2000 |
X |
|
|
|
|
|
14k
euros |
CSG
+ CFG |
None |
Oct 03 |
AOControl
Replacement |
2 | 376 |
Increase
network bandwidth and communications between NAVIS and the C40’s |
X |
|
|
|
|
|
|
CSG
+ CFG |
Durham
(1 week) |
Oct 03 |
FELIX |
2 | 378 |
Allows
simultaneous flattening and phasing of DM |
X |
|
|
X |
|
|
|
TG |
None |
Apr 04 |
Measuring
Response of Tip Tilt |
3 | 214 |
Information
Required for feed-forward algorithm |
|
X |
|
|
|
|
|
SG & TG (2 days) |
None |
Oct 03 |
Placing
NAOMI into CVS |
2 | 361 |
Migration
version control from BCS to CVS ‘ING standard’ |
|
|
|
|
X |
|
|
CB
& SG |
Durham
(Phone support) |
Sep 03 |
Upgrade
68k processors to PowerPC’s |
2 | 379 |
Allow
NAOMI mechanism control software to be developable and maintainable
under ‘ING standard’ |
|
|
|
|
X |
|
|
SG |
OSL (4 weeks) |
Oct 03 |
Acquisition
Tools |
1 | 380 |
Allow
for the acquisitions of stars using the new Data Acquisition Camera |
|
|
X |
X |
|
|
|
CB |
|
Oct 03 |
Investigating
Replacing C40 with C67 |
2 | 381 |
Increase
frequency of real time band width on SG and WFS processors. |
|
X |
|
|
|
TBD |
TBD |
SG (1 week) |
|
Dec 03 |
TopGui
Upgrades |
2 | |
TopGUI
changes as requested by NAOMI team. |
|
|
X |
|
|
|
|
|
Durham
(2 weeks) |
|
L3
WFS replacement |
1 | 382 |
Replace
one of the NAOMI WFS with a low light level CCD |
X |
|
|
|
|
|
|
|
|
Apr 04 |
AO
Control GUI |
1 | 374 |
Reduce
the number of AO GUI’s currently used when setting up the system and
observing. |
|
|
X |
|
|
Manpower |
|
|
|
Apr 04 |
Simplex |
1 | 226 |
Improving
Software Communications between the simplex application and the detector |
X |
|
|
|
|
|
|
|
|
Aug 03 |
New
WFS modes |
1 | 383 |
Implement
new WFS to improve the faint guiding limit. |
X |
|
|
|
|
|
|
SG & |
ATC (1 week) |
Oct 03 |
Temperature Compensation Tests | 1 | 384 | Investigate the effects of temperature of the DM | |
X | |
|
|
|
|
SG & SE | |
Dec 03 |
Remove Fan from INGRID SDSU controllers | 2 | 385 | Reduce the effect of the fan in the INGRID SDSU Controller | |
|
|
|
|
|
|
AH | |
Oct 03 |
FISBA spiral fringe search algorithm | 2 | 228 | Software to hunt for dm elements that have strayed out of sight | |
|
X | X | |
|
|
CB | |
Oct 03 |
Derotator optics | 1 | 269 | To purchase, coat and install new derotator optics | |
|
|
|
|
|
|
TG | |
Dec 03 |
Doubling the Strain Gauge feedback loop | 1 | 389 | Algorithm to double the strain gauge frequency loop | |
|
|
|
|
|
|
SG | |
Aug 03 |
ND Filters | 2 | 390 | Purchase and install ND 1&2 filters into WFS | |
|
|
|
|
|
|
TG | |
Oct 03 |
Key
PG - Performance Gains
LPG - Leads to Performance Gains
IUF - Increases User Friendliness
RST - Reduces Set-up Time
IM - Instrument Maintenance
CSG - Control Software Group
CFG - Computer Facilities Group
TG - Tom Gregory
SG - Stephen Goodsell
CB - Craige Bevil
AH - Andy Hide
SMT - Simon Tulloch
NAD - Nigel Dipper
SE - Sebastian Els
OSL - Observatory Sciences Limited
Created by Stephen Goodsell
sjg@ing.iac.es |