NAOMI Semester 03B Engineering Program

 
The following table shows the taks that are planned to be tackled during the 03B semester.  Each task has been placed into the Project Issue Management System (PIMS).  Each task has a link which should given more information on the task.  This should be a way of keeping up to date on the progress of each issue.  Everyone is encouraged to use PIMS.

 

Task

Priority

PIMS 

Issue

Description

PG

LPG

IUF

RST

IM

Risks

Cost

ING Effort

External Effort

Due By

NAVIS Upgrade

2 375

Replacing NAVIS with a dual 1.2GHz, 2Gb DIMM Sunblade 2000

X

 

 

 

 

14k euros

CSG + CFG (1 week)

None

Oct 03

AOControl Replacement

2 376

Increase network bandwidth and communications between NAVIS and the C40’s

X

 

 

 

 

 

 

CSG + CFG (1-2 weeks)

Durham (1 week)

Oct 03

FELIX

2 378

Allows simultaneous flattening and phasing of DM

X

 

 

X

 

 

 

TG

None

Apr 04

Measuring Response of Tip Tilt

3 214

Information Required for feed-forward algorithm

 

X

 

 

 

 

 

SG & TG 

(2 days)

None

Oct 03

Placing NAOMI into CVS

2 361

Migration version control from BCS to CVS ‘ING standard’

 

 

 

 

X

 

 

CB & SG

Durham (Phone support)

Sep 03

Upgrade 68k processors to PowerPC’s

2 379

Allow NAOMI mechanism control software to be developable and maintainable under ‘ING standard’

 

 

 

 

X

 

 

SG

 

OSL 

(4 weeks)

Oct 03

Acquisition Tools

1 380

Allow for the acquisitions of stars using the new Data Acquisition Camera

 

 

X

X

 

 

 

CB

 

Oct 03

Investigating Replacing C40 with C67

2 381

Increase frequency of real time band width on SG and WFS processors.

 

X

 

 

 

TBD

TBD

SG 

(1 week)

 

Dec 03

TopGui Upgrades

2

TopGUI changes as requested by NAOMI team.

 

 

X

 

 

 

 

  NAD

Durham (2 weeks)

Sep 03

L3 WFS replacement

1 382

Replace one of the NAOMI WFS with a low light level CCD

X

 

 

 

 

 

 

  SMT

 

Apr 04

AO Control GUI

1 374

Reduce the number of AO GUI’s currently used when setting up the system and observing.

 

 

X

 

 

Manpower

 

  CSG

 

Apr 04

Simplex

1 226

Improving Software Communications between the simplex application and the detector

X

 

 

 

 

 

 

  CB

 

Aug 03

New WFS modes

1 383

Implement new WFS to improve the faint guiding limit.

X

 

 

 

 

 

 

SG & Gao

ATC 

(1 week)

Oct 03

Temperature Compensation Tests 1 384 Investigate the effects of temperature of the DM
X




SG & SE
Dec 03
Remove Fan from INGRID SDSU controllers 2 385 Reduce the effect of the fan in the INGRID SDSU Controller






AH
Oct 03
FISBA spiral fringe search algorithm 2 228 Software to hunt for dm elements that have strayed out of sight

X X


CB
Oct 03
Derotator optics 1 269 To purchase, coat and install new derotator optics






TG
Dec 03
Doubling the Strain Gauge feedback loop  1 389 Algorithm to double the strain gauge frequency loop






SG
Aug 03
ND Filters 2 390 Purchase and install ND 1&2 filters into WFS






TG
Oct 03

 

Key

 

PG - Performance Gains

LPG - Leads to Performance Gains

IUF - Increases User Friendliness

RST - Reduces Set-up Time

IM - Instrument Maintenance

CSG - Control Software Group

CFG - Computer Facilities Group

TG - Tom Gregory

SG - Stephen Goodsell

CB - Craige Bevil

AH - Andy Hide

SMT - Simon Tulloch

NAD - Nigel Dipper

SE - Sebastian Els

OSL - Observatory Sciences Limited




Created by Stephen Goodsell