MONTHLY PROJECT REPORT
PROJECT : NAOMI MONTH Aug-03 AUTHOR SJG
SUMMARY        
Between the 9th to 23rd July, and 9th to 16th August NAOMI was on sky for the use of either
INGRID, OSCA or OASIS. - See CRB for on-sky performance
SOFT ANALYSIS
Successes:
Electrical Earthing - Andy Hide
Increasing the Simplex Speed - CB
Opportunities:
Failures:
Threats:
Engineering Manpower and Financial Resources still limit the Engineering Program
STATUS OF PROJECT MILESTONES
Current Plan Scheduled Latest Actual Change
NAVIS Upgrade Oct-03      
AO Control Replacement Oct-03      
Artificial Guide Star Oct-03      
FELIX   Dec-03      
Measuring Response of Tip Tilt Jul-03 Oct-03    
Placing NAOMI into CVS Sep-03      
Upgrade 68K to PowerPC Oct-03      
Acquisition Tool Oct-03      
Investigating replacing C40 with C67 Dec-03      
Top GUI Upgrades Sep-03      
L3 WFS Replacement Apr-04      
AO Control GUI Apr-04      
Speeding Up Simplex Jul-03   Aug-03  
New WFS Modes Oct-03      
Temperature Compensation Algorithm Investigation Dec-03      
Remove Fan From INGRID Oct-03      
Double Feedback Loop Bandwidth Jul-03 Aug-03    
           
Notes:  The scheduled date is that predicted by the current project plan. The latest column indicates the latest
estimated completion date.  Change indicates the delay (+) or recovery (-) since the last report


Created by Stephen Goodsell