THE ISAAC NEWTON GROUP OF TELESCOPES | |||||
MONTHLY PROJECT REPORT | |||||
PROJECT | : NAOMI | MONTH | Aug-03 | AUTHOR | SJG |
SUMMARY | |||||
Between the 9th to 23rd July, and 9th to 16th August NAOMI was on sky for the use of either | |||||
INGRID, OSCA or OASIS. - See CRB for on-sky performance | |||||
SOFT ANALYSIS | |||||
Successes: | |||||
Electrical Earthing - Andy Hide | |||||
Increasing the Simplex Speed - CB | |||||
Opportunities: | |||||
Failures: | |||||
Threats: | |||||
Engineering Manpower and Financial Resources still limit the Engineering Program | |||||
STATUS OF PROJECT MILESTONES | |||||
Current Plan | Scheduled | Latest | Actual | Change | |
NAVIS Upgrade | Oct-03 | ||||
AO Control Replacement | Oct-03 | ||||
Artificial Guide Star | Oct-03 | ||||
FELIX | Dec-03 | ||||
Measuring Response of Tip Tilt | Jul-03 | Oct-03 | |||
Placing NAOMI into CVS | Sep-03 | ||||
Upgrade 68K to PowerPC | Oct-03 | ||||
Acquisition Tool | Oct-03 | ||||
Investigating replacing C40 with C67 | Dec-03 | ||||
Top GUI Upgrades | Sep-03 | ||||
L3 WFS Replacement | Apr-04 | ||||
AO Control GUI | Apr-04 | ||||
Speeding Up Simplex | Jul-03 | Aug-03 | |||
New WFS Modes | Oct-03 | ||||
Temperature Compensation Algorithm Investigation | Dec-03 | ||||
Remove Fan From INGRID | Oct-03 | ||||
Double Feedback Loop Bandwidth | Jul-03 | Aug-03 | |||
Notes: The scheduled date is that predicted by the current project plan. The latest column indicates the latest | |||||
estimated completion date. Change indicates the delay (+) or recovery (-) since the last report | |||||
Created by Stephen Goodsell