NAOMI Wavefront-Sensor PDR
Requirements
wht-naomi-84
Internal document AOW/WFS/RAH/1.0/09/96 Wavefront Sensor PDR
Requirements
Versiondate: 18/09/96
1. Drawings
Preliminary drawings of the WFS and calibration source(s) approaching
the assembly level shall be supplied. Outlines of commercially available components
such as motors are acceptable provided the components are identified, i.e.
manufacturer, model number, with basic characteristics or data sheets available
as back-up. Drawings indicating preliminary cable layouts and component
locations on the optical table shall be provided. The cable routes to the
electronics racks shall be indicated. Any limitations on cable lengths that may
severely restrict the freedom to reposition key components should be pointed
out. Sufficient information is needed to prove that interface and space
requirements have been satisfied.In particular the choice of optical-axis
height shall be clearly shown. If the design goal of 150 mm has not been
achieved then the case for the selected height must be presented.
Information shall be presented on the adequacy of the space nominally
allocated to the tip/tilt sensor upgrade. If the initial allocation has been
found inadequate a drawing should be available showing the requestedallocation.
Where an assembly-level drawing does not provide sufficient detail or
clarity to convey the operation or nature of mechanisms, adjustments or key
components, simple drawings or artist’s concepts are acceptable although
detailed design drawings are preferred.
2. Optical Design
Details of the optical layout, e.g. component locations, sizes, radii,
thicknesses, material types, characteristics of lenslet arrays, etc. and
performance predictions are required. The predicted ADC performance as a
function of zenith angle and spectral bandwidth should be provided. Sufficient
tolerancing of optical components to at least define adjustment ranges and the
resolution of the adjustments is required. Machining tolerances for lenses
mounted in cells are not required at this stage.
Spectral transmission predictions and information on proposed coatings,
e.g. coating supplier and coating type, should be presented in sufficient
detail to demonstrate that the throughput specifications will be satisfied.
Representative spectral transmittance (or reflectance) curves for the coatings
should be available if requested.
3. WFS Performance Predictions
The results of predictions of the overall WFS performance for the
conditions specified in work package are required. In particular the
measurement ranges and phase-gradient accuracy shall be addressed. The
performance predictions shall take into account factors such as the lenslet
aberrations, CCD readout noise, errors in calibrating the CCD.
A preliminary analysis of thermal and vibrational sensitivities shall
be presented. This work must be taken to at least the level where any potential
problems can be anticipated. Any other potential problems associated with the
GHRIL environment must be identified. Proposed solutions to these problems
shall be presented if available.
4. CCD and Controller
Recommendations on the choice of CCD chip with key performance
parameters (quantum efficiency, noise, number of ports, etc.) shall be
presented. The size and general characteristics of CCD camera head including
power requirements, cooling, etc. are also needed. The choice of controller and
a review of any options shall be presented. The ability to meet requirements
such as the switchable readout rate, binning, shall be addressed.
5. Electronics
All major aspects of the electronics design and interfaces for the WFS
(not previously addressed in Section 4) shall be covered, e.g. motors, drivers,
power supplies, rack configuration, etc. Any anticipated problems or measures
related to EMC shall be identified.
The cooling method and plan for the electronics racks must be
presented.
NOTE: As the cooling method(s), overall electronics layout and cabling
are the responsibility of the Optical Chassis WP, any designs presented here
should have been agreed previously with the Optical Chassis WP Manager.
6. Software
The proposed software architecture, systems and interfaces should be
presented, together with an improved estimate of the effort needed. The
interface between the WFS software work and the RTCS processing of WFS data and
the responsibilities for each should be clearly defined. Note that only the
software required for WFS mechanism control and laboratory testing should be
addressed.
7. Weights
Weight estimates for all major mechanical, optical and electronic
sub-systems are needed, i.e. the WFS assembly, calibration source(s),
electronics modules, etc.
8. Alignment and Calibration
Plans for the WFS internal alignment and the alignment to the optical
chassis must be described.
The approach to the WFS calibration must be described in sufficient
detail to establish that the WPD requirements will be satisfied, i.e. design
and functionality should be covered.
9. Testing
An outline of plans for testing and integration is required. The outline must cover testing as a subassembly
and testing when integrated with the complete system both in the UK and at La
Palma. The need for any special test equipment or facilities should be
addressed, together with an estimate of the additional cost if available
10. Facility Requirements
The power, cooling requirements and predicted heat dissipation of all
major subassemblies shall be provided.
Any special handling or storage requirements must be identified.
11. Documentation
A preliminary list of documentation that will be provided on or before
delivery is required.
12. Miscellaneous Topics
These may include comments on the expected reliability of components
and need for spare parts, safety and handling, etc. Any components requiring
ING approval must be identified and approval for their use should have been
received from ING.
13. Future Work
The latest schedule with key milestones should be presented.
Critical-path items shall be clearly identified. Updated cost estimates and
profiles are needed.
Any further analyses or trade studies of significance still required or
recommended shall be briefly addressed.
Any anticipated high risk or problem areas shall be identified (if not
addressed elsewhere in the presentation), together with any proposed solutions.