ELECTRA and NAOMI Project Milestones.                                   wht-naomi-66

 

Internal Document Number AOW/MAN/AJL/4.7/10/97/ELECTRA-NAOMI Milestones

Version date  16/10/97, based on Project Plan version NAOPL997_2.MPP

 

Milestone

 

Due Date 11/07/96

Due Date 15/01/97

Due date 20/06/97

Due date 15/10/97

Achieved Date

Reason for delay

Single actuator DM test

D

25/03/96

25/03/96

08/03/96

08/03/96

08/03/96

 

E0 DM 10 segment soak test

D

30/07/96

11/10/96

11/10/96

11/10/96

11/10/96

Effort not available

ELECTRA WFS cam. delivery

D

09/08/96

17/01/97

20/01/97

20/01/97

20/01/97

Contractor late delivery

EEV chip delivered

D

15/08/96

22/08/96

22/08/96

22/08/96

22/08/96

 

tip-tilt mirror tested*

D

14/09/96

31/01/97

14/02/97

14/02/97

14/02/97

 

E0 first light

D

15/10/96

20/04/97

18/06/97

18/06/97

18/06/97

Revised definition of E0

Late delivery of WFS

E0 performance assessment

D

28/10/96

01/06/97

24/07/97

24/07/97

 

                 

Supervisory software Architecture Des. complete

C

28/10/96

28/04/97

28/04/97

28/04/97

28/04/97

Still preliminary as ING sys. architecture not fixed

o-m-c PDR

E

01/11/96

13/03/97

23/04/97

23/04/97

23/04/97

Staff changes; additional work on calibration unit; tighter PDR definition

WFS PDR

C

13/12/96

19/02/97

19/02/97

19/02/97

19/02/97

Revised WFS design

system review (1)

A

06/01/96

23/05/97

29/08/97

22/09/97

22/09/97

Delay to E0; changes in infrastructure assumptions; Modified to detailed progress report

Sup.S/ware prototype N-A built

C

24/01/97

03/06/97

01/08/97

31/01/98

 

Waiting for WHT Software Architecture development

OMC  CDR

E

14/03/97

21/08/97

09/09/97

07/11/97

 

Delayed PDR; lack of electronics effort

NAOMI WFS CCD delivery

C

-

-

13/10/97

12/12/97

 

 

NAOMI WFS CDR

C

11/04/97

11/09/97

14/11/97

17/12/97

 

Re-design to meet WFS spec latency with existing cam.

E1 closed loop DM accept

D

23/05/97

01/08/97

??

20/05/98

 

E0 delay: Durham grant delay.  New timescale awaiting feedback from E0

E1 lab acceptance

D

13/06/97

22/08/97

??

03/06/98

 

See above

system review (2)

A

30/06/97

06/11/97

16/02/98 ?

02/04/98

 

 

E1 can be at telescope

D

04/07/97

12/09/97

05/12/97 ?

17/06/98

 

E0 delay etc. New timescale awaiting feedback from E0

E1 performance evaluation

A

08/08/97

17/10/97

12/01/97 ?

22/07/98

 

See above

OAPs delivered

E

01/09/97

21/02/98

23/02/98

06/08/98

 

Latest quote gives 5 month delivery, instead of 3 months

Stubbed system software tests prototype  N-B

C

24/12/97

05/01/98

15/03/98 ??

31/08/98

 

Provisional pending further architecture definition

NAOMI WFS build complete

C

06/03/98

29/04/98

15/09/98

13/10/98

 

Funding profile changes

OMC stand-alone accept

E

13/03/98

01/09/98

21/06/99 

05/03/99

 

Reduction in stand-alone testing period, as expected after PDR.

NAOMI timing prototype N-C complete

C

10/06/98

26/06/98

??

26/03/99

 

Very provisional, pending further architecture information

WFS acceptance

C

15/06/98

31/08/98

24/02/99

11/01/99

 

 

NAOMI Full Lab. Integration starts

A

03/07/98

10/09/98

05/04/99

06/04/99

 

 

Full Lab. Integration complete

A

25/09/98

18/01/99

30/07/99

12/08/99

 

 

NAOMI First Light

L

14/11/98

05/03/99

22/08/99

14/09/99

 

 

 

 

Notes on 16/10/97 version

The design reviews held so far have proved the ideas for NAOMI are sound.

 

The following list itemises the main reasons for delays.   Some items have significant delays from the last plan, but only those relevant to ELECTRA and software prototyping are crucial, as the ELECTRA development and the top-level software are now the critical path items. There is about one month slack in other areas relative to this.

 

Overall delays have been caused by the following.

1.     Neither of the two cameras most likely to be available for the NAOMI WFS met the full latency specifications for NAOMI. A new option, to use two CCDs and bin pixels orthogonally in each CCD, has been evaluated and adopted to overcome this problem. The new option enables NAOMI to employ the new standard cameras to be adopted by ING while meeting NAOMI specifications.

2.     System reviews are further delayed because of (a) the delay to E0; (b) uncertainties in the infrastructure requirements at GHRIL;  (c) lack of  electronics effort

3.     Software planning has been hampered by continued uncertainties in the architecture to which NAOMI must interface. To recover (partially) from this the NAOMI internal architecture is now more tied to that of ELECTRA; the differential work in going from ELECTRA to NAOMI has been minimised, which should allow some flexibility in handling NAOMI development while the WHT architecture is determined and problems with DRAMA are evaluated and solved or by-passed.

4.     Delays to E0  have occu rred because it took longer to solve some real-time control problems than was anticipated.

5.     Delays to E1 are because of a combination of delay in delivery of the final verison of the WFS camera, the delay in awarding the Durham NAOMI grant and the delay to E0.

6.     Some additional delay is being caused by modifications to the funding profiles (June 1996). The current plan has a funding profile which is slightly delayed from that agreed in June, mostly because of the phasing of payments in the Durham grant but also because of a longer than expected delivery time on the OAPs.