Instrument Change Checklist
ISIS
Andy Ridings 19th March 2007
Revision 1.5
Renee Pit 2nd Nov 2009
Jürg Rey, 9/07/2010
Revision 1.8
| Tick each box when complete |
Tick box |
| 1. The handling trolley for the instrument to be
removed from the telescope must be lifted to the observing floor. |
|
| 2. ISIS should be lifted up to the observing floor. The
top of the handling frame can be removed so that the instrument is ready
to be mounted. |
|
| 3. Any electronic equipment, cabling or cryostats not
on the telescope should be taken to the observing floor. |
|
| 4. Any cryostats that are fitted to ISIS that are not
in use elsewhere should be mounted and the micrometers set-up. |
|
| 5.Clean ISIS slit. (Only clean it if you have been trained; otherwise contact a specialist) | |
| Preparation Complete
Signature :
Date : |
|
| Tick each box when
complete |
Tick box |
| 1. IMPORTANT Position the telescope for change: PARK
ZENITH |
|
| 2. Make entry in log book:
DO NOT MOVE TELESCOPE |
|
| 3. Lock off the telescope (Control Room). |
|
| 4. Turn the Cassegrain rotator to correct angle and
line up the marks on ISIS and the A&G box. |
|
| 5. Put telescope ties in on the GRACE side. |
|
| 6. Remove all connections to the instrument to be
removed. |
|
| 7. Move instrument handling trolley under instrument,
align & attach. |
|
| 8. Unbolt and remove instrument. |
|
| 9. Check that ISIS lid is open. |
|
| 10. Move ISIS into place and bolt on. ONE person
only to check all bolts are tight. |
|
| 11. Lift down and store trolley. |
|
| 12. Balance telescope. NB this should be done after
cabling up and switching on ISIS and the CCD controllers. Pre-testing
can then be carried out during balancing. |
Instrument Cabling
| Tick each box when complete |
Tick box |
| 13. Connect the ISIS air supply. |
|
| 14. Connect the ISIS 4MS Network and Engineers' ports
to the portserver and the RS232 box (labelled ISIS) respectively. |
|
| 15. Connect the ISIS EPICS crate to the DECNET. |
|
| 16. Connect and switch on the ISIS mains. |
|
| 17. Switch on : ISIS 4MS, ASL unit, ISISP EPICS crate
and SMDM 24v power supply. |
ISIS CCD mounting
| Tick each box when complete |
Tick box |
| 18. Clean the CCD Cryostat windows. |
|
| 19. Clean the camera lenses. |
|
| 20. Ensure the correct length filler tube is fitted in
each cryostat. HALF LENGTH tubes are needed for cryostats mounted on RED
and BLUE. |
|
| 21. Set the capstans A, B & C and the rotation for each
cryostat using the micrometers as per the 'Capstan Settings Book'. |
|
| 22. Clamp the capstans in correct order i.e. 1st A -
the hole, 2nd B - the slot, 3rd C - the flat. To PREVENT FORMING AN
EARTH LOOP: Ensure the micrometers including the D rotation micrometer are wound back and are not touching the frame. Also check that the clamps have insulating material fitted where they make contact with the capstan screws. CHECK isolation using a multimeter before connecting any cables to the cryostat. |
|
| 23. Connect air and set cryostat window flushing to ~50
litres/hour. |
ISIS CCD connections
| Tick each box when complete |
Tick box |
| 24. Connect the mains to the RED SDSU PSU. |
|
| 25. Connect an SDSU power cable between the RED SDSU
controller and the RED SDSU controller PSU. |
|
| 26. To be done be member of detector group taking
anti-static precautions: Connect the RED CCD main signal cable
static protection box to the RED SDSU controller. |
|
| 27. Connect the RED temperature cable between the RED
SDSU controller and the RED cryostat. |
|
| 28. Connect the RED shutter cable from ISIS RED shutter
to the RED shutter control box and the other shutter cable from the the
RED shutter control box to the RED SDSU controller. |
|
| 29. Connect an ID cable between the RED cryostat and
the RED SDSU controller. |
|
| 30. Connect the 2 fibres from the RED controller back
to the appropriate SPARC in the control room. |
|
| 31. Connect the mains to the BLUE SDSU PSU. |
|
| 32. Connect an SDSU power cable between the BLUE SDSU
controller and the BLUE SDSU controller PSU. |
|
| 33. To be done be member of detector group taking
anti-static precautions: Connect the BLUE CCD main signal cable
static protection box to the BLUE SDSU controller. |
|
| 34. Connect the BLUE temperature cable between the BLUE
SDSU controller and the BLUE cryostat. |
|
| 35. Connect the BLUE shutter cable from ISIS BLUE
shutter to the BLUE shutter control box and the other shutter cable from
the the BLUE shutter control box to the BLUE SDSU controller. |
|
| 36. Connect an ID cable between the BLUE cryostat and
the BLUE SDSU controller. |
|
| 37. Connect the 2 fibres from the BLUE controller back
to the appropriate SPARC in the control room. |
|
| 38. Switch on RED and BLUE SDSU controller PSUs and
Shutter control PSUs. |
ISIS post installation checks
| Tick each box when complete |
Tick box |
| 39. Coffee Break. |
|
| 40. At the instrument engineering terminal switch box
(right knob) select CASS INST. and using the right hand VT220 terminal
type .SLINKS This will test communication to each of the SMDMs and the encoder channels. Any faulty serial links will be listed. A faulty link to SMDM M ( that's a CAPITAL M ) can be ignored. |
|
| 41. Still at the engineering terminal type ILS
and CONFIG. These both give useful information about the health
of the instrument. |
|
| 42. At the telescope use the buttons on the front of
the RED and BLUE shutter control boxes to test the operation and status
from the shutters. |
|
| 43. Bring up a window on the ICS and type ping isisp
to check that the Epics ISIS Polarisation crate is on the network. |
Final checks though ICL and ICS
| Tick each box when complete |
Tick box |
| 44. Edit the detector configuration (DEWARS web page). |
|
| 45. Restart the observing system.. |
|
| 46. Update the magnet board. |
| Check each mechanism and tick each box
when complete |
Tick box |
| Open the
grating doors and check that each set of grating clamps works
correctly. Then ensure that the clamps are on before closing the
door. 47. Red Grating (this should only be done after a change and not mid-run; you will be disturbing the instrument set-up). By default use the R158R grating and then use the command: setgrating red r158r |
|
| inrg | |
setgratingorder red 1 |
|
| cenwave red 4500 | |
| cenwave red 6500 | |
| 48. Red Collimator (this should only be
done after a change and not mid-run; you will be disturbing the
instrument set-up). |
|
| inrcoll | |
| rcoll 28000 | |
| rcoll 9100 | |
| 49. Red Fold |
|
| ensure the Red Fold is IN (4MS: FDR SEE; position 1; no fault, don't move) | |
| 50. Red filter A |
|
| isis_init -m REDFILTERA | |
| rfilta 2 | |
| rfilta 1 | |
| 51. Red Filter B |
|
| isis_init -m REDFILTERB | |
| rfiltb 1 | |
| 52. Red Hartmann Shutter |
|
| rhart 3 | |
| rhart 0 | |
| 53. Blue Grating (this should only be
done after a change and not mid-run; you will be disturbing the
instrument set-up). By default use the R300B grating and then use
the command: setgrating blue r300b |
|
| inbg | |
| setgratingorder blue 1 | |
| cenwave blue 6500 | |
| cenwave blue 4500 | |
| 54. Blue Collimator (this should only be
done after a change and not mid-run; you will be disturbing the
instrument set-up ) |
|
| inbcoll | |
| bcoll 28000 | |
| bcoll 5200 | |
| 55. Blue Fold |
|
| inbfold | |
| bfold 2 | |
| 56. Blue Filter A |
|
| isis_init -m BLUEFILTERA | |
| 57. Blue Filter B |
|
| isis_init -m BLUEFILTERB | |
| 58. Blue Hartmann Shutters |
|
| bhart 3 | |
| bhart 0 | |
| 59. Slit Carriage Unit |
|
| mslit | |
| longslit | |
| 60. Set Slit Width (this should only be
done after a change and not mid-run; you will be disturbing the
instrument set-up ) |
|
| slit 100 | |
| slit 5000 | |
| slitarc 1.0 | |
| 61. Dekker Slide | |
| indek | |
| dekker n (where n = 1 ... 8; use 'dekker 8'
by default) |
|
| 62. Field Lens, Calcite Block and
Polaroid Tray |
|
| infcp | |
| isis_move -m fcptray polaroid | |
| isis_move -m fcptray fieldlens | |
| isis_move -m fcptray calcite | |
| isis_move -m fcptray clear | |
| 63. Slit Door ( NB the dekker must be at
position 1 for access to the slit area ) |
|
| slit_door unlock | |
| slit_door lock | |
| 64. Quarter Wave Plate |
|
| inqw | |
| isisp_move -m PQWSLIDE in | |
| isisp_move -m PQWSPIN 0.5 | |
| isisp_move -m PQWSPIN 0 | |
| isisp_move -m PQWANGLE 10 | |
| isisp_move -m PQWANGLE 300 | |
| isisp_move -m PQWSLIDE out | |
| 65. half Wave Plate |
|
| inhw | |
| isisp_move -m PHWSLIDE in | |
| isisp_move -m PHWSPIN 0.5 | |
| isisp_move -m PHWSPIN 0 | |
| isisp_move -m PHWANGLE 10 | |
| isisp_move -m PHWANGLE 300 | |
| isisp_move -m PHWSLIDE out | |
| Take an arc with each arm. If arc lines are obtained
then it is time to hand over to the SA to perform the final
focussing. |
|
| INSTRUMENT CHANGE COMPLETE Signature: Date: |
|
| HANDOVER TO SUPPORT ASTRONOMER
Signature:
Date: |
|
Revision History:
KMD Revision 1.3 clean slit added.
AWR Revision 1.4 transition from ICL to Unix ICS
AWR Revision 1.5 grating order added
RJP Revision 1.6 isisp commands updated
JR Revision 1.7 inhw added and minor corrections
JR Revision 1.8 only check red fold; don't move